Schedule

Schedule

MAIN TASKS Spring 2020:

  • Spring timeline/Gantt Chart
  • Research: Update research; focus on a research question for your project
  • Project:  the capstone project itself
  • Media Night presentation: How you will present your capstone project
  • Documentation: weekly web journal, notes, sketches, photos, video–anything that will help you document your process; this is helpful for your final video
  • Video: 3-5 minute video documentation of your project
  • Poster, Logo/Press or Outreach to audiences
  • User testing and/or feedback
  • Web feature about your project–done by NMD 343 student for NMD website
  • Portfolio
Week 1: Jan 21
Discussion, Feedback, Brainstorming with Other Capstone Class
Week 2: Jan 28
  • Gantt Charts
  • Web Portfolio
Week 3: Feb 4
Milestone 4 B & C
Week 4: Feb 11
Milestone 4 D & A
Week 5: Feb 18
Milestone 5 C & D
Week 6: Feb 25
Milestone 5  A & B
Week 7: Mar 3*
User Testing & Feedback
Week 8: Mar 10
Results of User Testing & Feedback
Week 9: Mar 17 Spring Break
Spring Break
Projects should be complete by Spring Break and have elicited the first round of user testing & feedback
Week 10: Mar 24
Web Portfolio & Posters
Week 11: Mar 31*
Capstone Video rough cut
Week 12: Apr 7
Milestone 6
Week 13: Apr 14
Milestone 6
Week 14: Apr 21
Poster & Video due
Week 15: Apr 28
Capstone presentation
Final capstone due by New Media Night
New Media Night April 30 or May 1